Plans for new building

The school is about to begin phase two of our building project to become a permanent three form entry. From late July work will begin to strip out the existing hall, toilets and staff areas in preparation to start the main demolition works in August. 

Week 1

The building site has been very busy this week, with initial ground works being completed and access from Witham Road being created. The children have enjoyed watching different machinery arriving on site and the fence being erected!

Week 2

On Thursday as we were walking through the corridor, we heard crunching noises as the old year 6 block was being knocked down. We saw the remaining wall of the art room with the original black board! We then watched the old year six block being demolished! They have also dug huge holes for the foundations!

By Joel, Evie S, Millie- May, Demee, Ayham and Erin, 3B

IMG_0866

Weeks 3 and 4

Lucky 4B got to go into the restricted building site to see the builders at work. We stood in amazement as we watched the large white truck pour the sloppy cement into the six foot deep holes.

Week 4 - Cement pour

Weeks 5 and 6

Further ground works were completed over the last two weeks in preparation for the steel frame. 

Week 5 - Holes 2

Weeks 7 - 10

The tower crane has been erected and is being used to assemble the steel frame!

Week 7 - Tower crane erectedWeek 8 - Erection of steel frame

Week 11

The metal decking has been placed on top of the steel frame.

Week 11 - Metal decking

Week 12

The first bricks on the new build have been laid!

Week 12 - First bricks

Week 13

There has been cement poured onto the roof ready for the playground!

Week 13 - roof cement pour

Weeks 14 and 15

The ground works have continued...

IMG_3141

Week 16

The view from the roof!

IMG_3242

Weeks 17 and 18

Screeding the rooftop playground

IMG_3348

Weeks 19 and 20

The new build is taking shape and we have had some visitors already to view the site!

WP_20170331_09_55_01_Pro_LI

Week 21

Windows and doors have begun to go in.

IMG_3699

Week 22

Underfloor heating is being fitted.

IMG_3694

Week 23

The Multi-Utility Games Area (MUGA) fence posts have gone in and the surface is being treated.

IMG_3894

Weeks 24 and 25

The new building is being insulated and partition walls are being put into place.

IMG_3983